How to Apply for Net Billing in Pakistan (2026): Green Meter Steps, Documents, Fees and Timeline
Step-by-step guide to getting a green meter under NEPRA's 2026 net billing rules: three-phase and sanctioned load checks, the 80% transformer limit, documents, the nil fee up to 25 kW, DISCO deadlines and common rejections.
Ahsan Sajjad · Published 18 November 2026
Short version: you apply to your electricity company (LESCO, IESCO, K-Electric and the others), not to NEPRA. You need a three-phase connection, a system no bigger than your sanctioned load, a transformer that isn't already full of solar, and a certified installer to file the papers. For systems of 25 kW or less there's no NEPRA fee and no NEPRA approval step, so your DISCO approves it. Until the green meter is fitted, keep your inverter on zero export. Size your system first with the solar calculator.
"Green meter kaise lagwayein?" is one of the most common questions after people buy panels, and it often comes too late. Most net billing problems are decided before a single panel goes on the roof: the wrong connection type, a sanctioned load that's too small, or a transformer the DISCO won't add more solar to. Then the system sits on zero export for months, or the bill goes up because an ordinary meter counts exported units as consumption.
This guide walks through the process as it works in November 2026 under the NEPRA (Prosumer) Regulations, 2026 and the amendments since, using NEPRA's own notifications and the DISCO portals. If you want to know what net billing pays and who still keeps old net metering, read our net metering vs net billing guide first. This one is about getting connected.
Before you start: four checks that decide everything
Do these before you pay an installer a deposit. Each one can stop an application on its own.
1. Is your connection three-phase?
The regulations define an applicant as a "3 phase 400V or 11kV" consumer (regulation 2(1)(v)). The interconnection agreement in Schedule-I says the same, and K-Electric's 2026 consumer application form repeats it. In plain terms, a normal single-phase house connection can't get net billing as it stands.
How to tell: a single-phase meter has two thick incoming wires (one phase and neutral), a three-phase meter has four (three phases and neutral), and three-phase bills usually show a higher sanctioned load. Our guide to three-phase vs single-phase solar shows more ways to check.
If you're single-phase, you first apply to the DISCO for a load extension and conversion to three-phase. The PITC net billing portal points consumers of IESCO, FESCO and other ex-WAPDA companies to the ENC portal (enc.com.pk) for this, and MEPCO consumers to their customer facilitation centre or the Power Smart app. That conversion has its own demand notice and wiring requirements, so budget time for it.
2. Is your sanctioned load big enough?
Under regulation 3(2), the capacity of your solar system can't exceed the sanctioned load of the premises. If your bill says 5 kW sanctioned load, a 10 kW system won't be approved until the load is increased first.
This is stricter than the old 2015 rules, which allowed up to one and a half times the sanctioned load. You'll still find old checklists online that say "1.5x", including some DISCO documents from 2025. For new applications under the 2026 regulations, plan on the system size and the sanctioned load matching.
Keep in mind that raising the sanctioned load to 5 kW or more moves most homes onto time-of-use billing, with a peak rate of Rs 46.85 per unit and an off-peak rate of Rs 34.53, plus a fixed charge of Rs 675 per kW. That's not a reason to avoid it, but it does change your bill. You can model both with the LESCO bill calculator, IESCO bill calculator or the general bill calculator.
3. Is your transformer already full?
This is the check almost nobody does. Under the proviso to regulation 3(5), the DISCO "shall not entertain" a new application if the solar capacity already connected to your distribution transformer has reached 80% of its rated capacity.
In housing societies and dense neighbourhoods where many homes went solar in 2024 and 2025, this is a real bottleneck. The PITC portal at nmp.pitc.com.pk (used by the ex-WAPDA DISCOs) has a "Check Transformer Overloading" option on its front page. Use it, or ask your installer to check, before you buy anything. K-Electric's own guidelines warn that transformer capacity limits can mean "consumer-funded augmentation", which means you may be asked to pay for the upgrade.
4. Is your installer certified?
DISCOs process net billing files from certified installers. The Alternative Energy Development Board (AEDB) was merged into the Private Power and Infrastructure Board (PPIB) in 2023, so certificates are now issued and listed by PPIB under the AEDB (Certification) Regulations, 2021. K-Electric's checklist asks for a "PPIB vendor certificate", and the PITC portal asks installers to attach the installer-customer agreement from the AEDB schedules.
Ask your installer for their certificate number, then find it on PPIB's latest list, check the validity date and the provinces it covers. An uncertified subcontractor working under someone else's name is a common reason files stall. You can compare local installers on our installers directory.
Step by step: from application to green meter
Regulation 3 sets a maximum time for each step. These are the limits your DISCO is supposed to meet. They aren't a guarantee, but they help when you need to chase a delayed file.
- Ask for the forms. The DISCO must give you its information and the approved documents free of charge within two working days (proviso to regulation 3(1)). In practice, the forms are also downloadable from the portals.
- Submit the application. For ex-WAPDA DISCOs (IESCO, LESCO, FESCO, GEPCO, MEPCO, PESCO, HESCO, SEPCO, QESCO, TESCO and HAZECO), applications go through the PITC net billing portal, where you or your installer can choose "Apply for Net Billing". If you apply as a consumer, the installer you choose then confirms the technical details and uploads documents. K-Electric customers apply on KE's net metering page and get a provisional case ID by SMS and email.
- Completeness check. Within five working days the DISCO acknowledges your application and tells you if anything is missing. You then have three working days to supply it (regulation 3(5)).
- Initial review. The DISCO checks technical feasibility within fifteen working days (regulation 3(6)). If it isn't feasible, the application is returned with reasons within three working days of that review.
- Agreement. If you qualify, you and the DISCO sign the interconnection agreement within seven working days (regulation 3(8)).
- Estimate (demand notice). Within seven working days of signing, the DISCO issues the connection charge estimate for the interconnection, including the meter (regulation 3(9)).
- Pay. You pay the estimate within seven working days of it being issued (regulation 3(10)).
- Meter and commissioning. The DISCO installs and commissions the interconnection within fifteen working days of payment (regulation 3(11)).
- Approval and billing. Net billing starts once approval is in place. For systems of 25 kW or less, the DISCO itself gives that approval (S.R.O. 1330(I)/2026). For systems above 25 kW, the DISCO sends your file to NEPRA for concurrence, which NEPRA may grant within seven working days of getting the documents (regulation 4(3)).
If every step uses its full limit, steps 3 to 8 add up to roughly 55 to 60 working days, or about three months, for a home system. That's the maximum on paper. Real files are often slower, especially with missing documents, a busy transformer or a load extension in the middle.
One more rule to know: once you have concurrence or approval, you have six months to start generating. Otherwise you need a fresh one (regulation 4(4)).
Documents you'll need
The exact list varies a little by DISCO, so check your DISCO's current checklist. For a normal home, expect the following:
- CNIC copy of the owner. The name and address should match the electricity bill. K-Electric says this explicitly.
- Latest paid electricity bill, in the same name. If the bill is still in a previous owner's or a relative's name, get the name changed at the SDO office or customer centre first. A name mismatch is one of the most common reasons files are sent back.
- Schedule-II application form (the standard application form). It asks for your details, the site address and coordinates, expected yearly consumption and generation, installer details, inverter make and model, a single-line diagram and the requested in-service date.
- Interconnection agreement (Schedule-I), signed with witnesses. Witness CNIC copies are often required as well.
- Installer-customer agreement in the AEDB/PPIB format, plus the installer's certificate.
- Technical data: panel and inverter data sheets. Grid-tied inverters have to comply with UL 1741 under regulation 9(5), so ask for proof that your model meets it.
- Single-line diagram and site plan, showing the manual disconnect switch. Regulation 9(4) requires a disconnect device "that has a visual break".
- Inverter settings on the installer's letterhead (K-Electric asks for this).
- For companies, mosques, trusts and similar: incorporation papers, NTN and an authority letter for the person signing.
- For systems of 250 kW or more: a load flow study (regulation 3(3)), plus an electrical inspector's certificate on the DISCO checklists.
Where NEPRA concurrence still applies (above 25 kW), the file also includes the Schedule-III concurrence application and an affidavit on Rs 50 non-judicial stamp paper (Schedule-V).
Fees and costs: what you actually pay
Three kinds of cost come up, and people often mix them up.
- NEPRA fee: nil for 25 kW or less. NEPRA's S.R.O. 709(I)/2026 (28 April 2026, effective from 9 February 2026) sets the concurrence fee at nil for systems of 25 kW or less and Rs 1,000 per kW (one time, paid to NEPRA) above 25 kW. So a 10 kW home pays NEPRA nothing, and a 40 kW factory roof pays Rs 40,000. Some older DISCO checklists still list a Rs 1,000 per kW pay order for every case. If yours asks for one on a home system, point to S.R.O. 709(I)/2026 and ask for the requirement in writing.
- DISCO estimate (demand notice). Under regulation 12, the prosumer pays for the interconnection up to the interconnection point, including the meter, plus any distribution work needed only for your connection. The amount comes on the DISCO's estimate, and it varies by DISCO, meter type and site. SolarRate.pk doesn't track these charges, so we don't quote a figure: price data unavailable. If the DISCO has no meter in stock, regulation 12(3) lets you buy one yourself, as long as the DISCO tests it before installation.
- Installer's paperwork charge. Many installers charge separately for filing the net billing file, or include it in the package. It should be its own line on the quotation so you can compare. Run any quote through Check my quote and our quotation checklist.
For the cost of the system itself, see the live 5 kW system price (currently about Rs 398,808 – 587,349 on-grid) or the 10 kW system price (about Rs 784,415 – 1,238,697). Both are built from today's dealer listings, not a quote.
Zero export until the green meter is in
This is the costliest mistake, so it's worth repeating. Until the bidirectional meter is installed and net billing is live, set your inverter to zero export (sometimes called "no feed-in" or "anti-backflow"). An ordinary meter can record exported units as consumption, so your bill rises even though you're giving electricity away.
Zero export doesn't make the system useless while you wait. Your panels still run the house during the day, and every unit you use yourself saves your full slab rate, for example Rs 36.46 per unit for a 400-unit unprotected home before taxes and adjustments. A hybrid inverter can also keep charging a battery. What you lose while waiting is only the export credit, which under net billing is currently Rs 8.13 per unit (April–June 2026).
Is net billing worth the paperwork?
Usually yes, but it matters less than it did under net metering. Each exported unit now earns Rs 8.13, while each unit you'd otherwise buy costs your slab rate. For a 400-unit home that gap is about Rs 28.33 per unit. Most of the saving comes from what you use yourself, not from the green meter.
That changes how you plan:
- Size for daytime use, not for export. A system that fits your daytime load does most of its work even on zero export. Our guide on sizing solar from your electricity bill explains how.
- Still apply if you'll export a lot. Homes that are empty during the day, or with a big roof and small daytime use, export much of their output. For them the green meter adds real value. See how many units solar produces to estimate your surplus.
- Factor in payback. Our solar payback guide shows how self-use changes the years: a 5 kW system pays back in about ~2.5 years at 80% self-use, against ~3.9 years at 40%.
Why applications get stuck or rejected
From the regulations and the DISCOs' own guidelines, the usual reasons are:
- Single-phase connection. Not eligible until converted to three-phase.
- System bigger than the sanctioned load. Either reduce the system or get the load extended first.
- Transformer at 80% solar. The DISCO can't take new applications on it. Ask whether augmentation is possible and who pays.
- Name mismatch between CNIC and bill, or unconfirmed roof ownership.
- Missing or old forms. Some DISCO websites still carried 2015 forms in 2026. Use the current Schedule-II and Schedule-I from the portal.
- Installer issues: an expired certificate, a certificate that doesn't cover your province, or a non-certified subcontractor.
- Site problems found on inspection: poor earthing, panels or inverter that don't match the application, an unfinished installation. K-Electric names all of these as grounds for rejection.
- Inverter not compliant with UL 1741, or export settings not as declared.
If your DISCO misses a deadline, complain in writing first and quote the regulation and dates. Keep your acknowledgement receipt and case ID. Under regulation 17, any dispute between a prosumer and the DISCO goes to NEPRA for decision.
Adding panels later
Under regulation 4(1), a prosumer needs fresh concurrence before any change to the system's technical parameters, and the PITC portal has a separate "DG Capacity Enhancement" application. So adding panels means another application, and the new total still can't exceed your sanctioned load.
If you're on an old net metering agreement signed before 9 February 2026, be extra careful. A "material modification" that changes maximum output can end your grandfathered terms and move you onto net billing. Our net metering vs net billing guide explains this in detail.
Common questions
Green meter kaise apply karein? Ex-WAPDA DISCO consumers (LESCO, IESCO, FESCO, MEPCO and others) apply on the PITC net billing portal, nmp.pitc.com.pk, directly or through a certified installer. K-Electric consumers apply on KE's website. You need a three-phase connection and a system no bigger than your sanctioned load.
Net metering ki fees kitni hai 2026 mein? NEPRA's fee is nil for systems of 25 kW or less, and Rs 1,000 per kW for bigger systems (S.R.O. 709(I)/2026). You still pay the DISCO's estimate for the meter and connection work.
Single phase par net metering ho sakti hai? Not under the 2026 regulations. The applicant has to be a three-phase 400V or 11kV consumer, so convert to three-phase first through a load extension application.
Green meter lagne mein kitna time lagta hai? On paper, roughly 55 to 60 working days from submission if every step takes its full limit. In practice it's often longer, especially with a load extension or a crowded transformer.
Kya NEPRA se approval leni padti hai? Not for 25 kW or less. Since S.R.O. 1330(I)/2026 (6 August 2026), your DISCO approves systems of that size itself. Above 25 kW, the DISCO forwards your file to NEPRA for concurrence.
Sanctioned load se bara system lag sakta hai? Not under net billing. Regulation 3(2) caps the system at the sanctioned load. Get the load increased first, then apply.
Green meter se pehle solar chala sakte hain? Yes, on zero export. The house uses the solar directly, and nothing is pushed into an ordinary meter.
Transformer full ho to kya karein? The DISCO can't accept a new net billing application on a transformer that's already at 80% solar. Ask in writing whether augmentation is planned or possible, and what it would cost you. Meanwhile, a zero-export system sized to your daytime load still cuts your bill.
اس گائیڈ کی قیمتیں ہماری ٹریک کردہ ڈیلر لسٹنگز سے خود اپڈیٹ ہوتی ہیں (آخری تازگی 19 نومبر 2026)۔ اشارہ جاتی مارکیٹ رینجز ہیں، کوٹ نہیں۔Prices update automatically from dealer listings we track (last refreshed 19 November 2026). Indicative ranges, not quotes.
Official sources
- NEPRA (Prosumer) Regulations, 2026, S.R.O. 251(I)/2026, 9 February 2026 (eligibility, sanctioned load limit, 80% transformer limit, step deadlines, documents, schedules): nepra.org.pk
- NEPRA S.R.O. 709(I)/2026, 28 April 2026 (concurrence fee: nil up to 25 kW, Rs 1,000 per kW above): nepra.org.pk
- NEPRA S.R.O. 1330(I)/2026, 6 August 2026 (DISCO approval instead of NEPRA concurrence for 25 kW or below): nepra.org.pk
- NEPRA quarterly adjustment decision, S.R.O. 1501(I)/2026, 7 September 2026 (net billing export rate): nepra.org.pk
- PITC net billing portal for ex-WAPDA DISCOs (applications, transformer check, forms, installer guidelines): nmp.pitc.com.pk
- K-Electric net billing guidelines, 13 April 2026: ke.com.pk
- PPIB (installer certification under the AEDB (Certification) Regulations, 2021; AEDB merged into PPIB in 2023): ppib.gov.pk
This guide explains the rules as published by NEPRA and the DISCOs as of 18 November 2026. It isn't legal advice. Procedures and checklists change, so confirm the current requirements with your DISCO before you apply.